Fabrication and erection of 600 MT overhead conveyor bridge structure including trusses, gantries, and walkways for Adani Group at Mundra, Gujarat.
GM Engineering & Project was awarded the structural steel package for an overhead conveyor bridge at Adani Group's facility in Mundra, Gujarat. The scope covered fabrication and erection of 600 MT of structural steel including trusses, gantries, walkways, and supporting structures for the conveyor system.
The project required erection of long-span bridge segments at height while maintaining precise alignment and structural stability "” all within an active plant environment. Our team coordinated closely with Adani's mechanical and electrical teams to ensure seamless integration with the conveyor system installation.
The project was completed within the scheduled timeline from June 2023 to February 2024, achieving precise structural alignment and zero major safety incidents throughout execution.
Erecting long-span conveyor bridge segments at significant height while maintaining precise structural alignment "” all within a continuously operating plant environment "” presented major safety and engineering challenges.