Structural Steel Completed

Industrial Warehouse Complex, Ahmedabad

Primary & secondary structural steel fabrication and erection for a 50,000 sq ft multi-bay industrial warehouse with mezzanine floors.

850 MT
Total Steel
6 Months
Duration
Ahmedabad
Location
2023
Year
Location
Ahmedabad, Gujarat
Total Tonnage
850 Metric Tonnes
Duration
6 Months (Jan–Jun 2023)
Client
Adani Logistics Ltd.
Project Overview

About This Project

GM Engineering & Project was awarded the complete structural steel package for the Adani Logistics Industrial Warehouse Complex in Ahmedabad. The project involved the design, fabrication, and erection of a 50,000 sq ft multi-bay warehouse facility with integrated mezzanine floors and a dedicated loading dock structure.

The structure comprised primary portal frames in IS 2062 Grade E250 mild steel, secondary purlins and girts in cold-formed sections, and a full mezzanine floor system with composite deck slabs. All fabrication was carried out at our Hansalpur facility and transported to site in pre-assembled modules to minimize erection time.

The project was completed 12 days ahead of schedule, with zero LTI (Lost Time Incidents), and passed all third-party quality inspections on first submission.

Scope of Work

What We Delivered

Primary Steel Structure
Portal frames, columns, rafters "” 620 MT IS 2062 E250 MS
Secondary Structure
Purlins, girts, bracing, eave struts "” 130 MT cold-formed sections
Mezzanine Floor System
Two-level mezzanine with composite deck, 8,000 sq ft per level
Loading Dock Structure
Canopy and dock leveller support frames "” 60 MT
Surface Treatment
Shot blasting Sa 2.5, 2-coat epoxy primer + polyurethane topcoat
Architectural Metalwork
Staircases, handrails, safety gratings, access ladders
Design & Drafting
Value engineering, shop drawings, GA drawings, erection sequence
Erection & Commissioning
Full site erection with 2 cranes, 45-person erection crew
Engineering Challenges

Challenges & Solutions

Tight Site Access & Congested Layout

The site was located within an active industrial estate with restricted crane swing radius and limited laydown area, making conventional erection sequences impractical.

Solution

We pre-assembled portal frame bents at our Hansalpur yard and transported them as complete units. A custom erection sequence was developed to allow sequential bay-by-bay erection using a single 80T crane, eliminating the need for a second crane on site.

Accelerated Schedule "” 20% Compression

The client required the structure to be ready for roofing contractor handover 3 weeks earlier than the original programme due to monsoon season constraints.

Solution

We ran parallel fabrication shifts (day + night) at our workshop and deployed an additional erection team. Detailed look-ahead scheduling ensured zero idle time on site. The structure was handed over 12 days ahead of the revised deadline.

High-Load Mezzanine Design Requirement

The client required the mezzanine to carry 10 kN/m² live load for heavy pallet racking "” significantly above standard warehouse design loads.

Solution

Our design team performed value engineering on the beam grid layout, optimising beam depths and spacing to achieve the required capacity while reducing steel tonnage by 8% compared to the initial design. Composite deck with 150mm concrete topping was specified for maximum stiffness.

Project Outcomes

Results That Speak

12
Days Ahead of Schedule
Delivered before revised deadline
0
Lost Time Incidents
Zero LTI across 6 months
8%
Cost Saving via VE
Value engineering on mezzanine design
1st
Pass on QC Inspection
All third-party checks cleared first time
Client Feedback
"

"GM Engineering delivered our warehouse structure ahead of schedule and within budget. Their team's technical knowledge, proactive problem-solving, and commitment to safety made them an outstanding partner. We've already awarded them our next project."

R
Rajesh Patel
Project Manager, Adani Logistics Ltd.